Client:School Board of Monroe County
Location :Marathon, Florida
Budget :$32,120,536.71
Architect :Harvard Jolly Architecture
Completion :August 2020

Monroe County Schools Stanley Switlik Elementary School

This project encompasses the partial replacement and renovations to an existing school, reconfigured and added parking areas and the addition of a bus maintenance facility totaling 87,554 SF.

The current two story administration building will be demolished and replaced by two buildings, a single story administration building and a two story classroom building. Another existing two story classroom building and the cafeteria building will be renovated. New construction is to be tilt wall panels with standing seam and metal roofs, impact windows and state of the art audio/visual systems in each classroom utilizing promethean boards and teaching walls. The site will be raised five feet above current conditions to address storm surge and potential flooding issues in the Florida Keys. The existing school will remain occupied and operational during construction requiring a multi-phased construction sequence.

Click HERE for the job site webcam.

CURRENT STATUS (as of 5/8/20)

Basketball court painting is 100% complete. Building 3 MEP rough in is 90% complete. Building 3 interior wall gypsum is 98% installed. Building 3 wall patching is 100% complete. Building 3 exterior stucco removal and replacement is 100% complete. Building 3 sprinkler system is 75% complete. Building 5 roof is 100% complete. Building 5 interior wall framing is 100% complete. Building 5 stucco is 95% complete. Building 5 MEP rough in is 98% complete. Building 5 interior walls are 100% final painted. Building 5 raised platforms/steps have been poured. Building 5 sprinkler sysytem passed inspection. Building 4 Stucco is complete and wall framing is 10% complete. Site canopy footers are 5% complete.