PROJECT DESCRIPTION:The work consists of projects on 5 different sites. Four of the sites include adding a prototype two story 10 classroom addition (approximately 16,500SF each), removing and relocating portables and adding covered walkways to the portables that are scheduled to be kept on site. The fifth site includes adding 10 portables with covered walkways to the portables. These projects include:
Skyview Elementary School - $5,420,000 to be completed in August 2009
Ponce de Leon Elementary School - $6,011,934 to be completed in November 2009
Oakhurst Elementary School - $4,309,166 to be completed in January 2010
Leila Davis Elementary School - $4,560,074 to be completed in January 2010
Seminole High School - amount and completion date TBD
CURRENT STATUS (11/15/08):Completing Design and Estimating
|