PROJECT DESCRIPTION:
The new facility will replace New College’s existing Palmer Buildings A, C, D, and E which currently contain a mix of academic and administrative spaces. Work of this project will consist of the design and construction of approximately 30,000 GSF (Gross Square Feet) of faculty offices, academic classrooms, business offices, general administrative offices and support facilities. Upon completion of construction and relocation from the Palmer Buildings, the existing structures will be demolished and the site restored. This will be a LEED certified project.
New College of Florida Web Cam
CURRENT STATUS (08/01/10):
Construction Update: The north 2nd floor truss bearing tie beam is complete and roof truss erection is ongoing on the low roof. The east 3rd floor truss bearing tie beam will be poured on 8/6, with trusses to follow. Floor polishing on the 2nd floor east leg is almost complete. Layout and framing is ongoing on the 2nd floor east leg with MEP rough-in to follow. MEP rough-in is ongoing on the 1st floor. Scaffold is currently being erected around the perimeter of the building to prepare for application of waterproofing system. The project is currently 40% complete and is on schedule.
|