PROJECT NAME: NASSAU COUNTY CALLAHAN MIDDLE SCHOOL RENOVATIONS




LOCATION:Callahan, FL
OWNER:Nassau County Schools
ARCHITECT:Clemons Rutherford & Associates, Inc.
BUDGET:$6,900,000
COMPLETION DATE: January 2010

PROJECT DESCRIPTION:The Callahan Middle School Project will include the following activities:
1. The construction of a 23,000 SF Cafetorium.
2. Complete interior demo, 4,500 square foot addition, and interior build out of the existing cafeteria. The newly renovated space will be a 10 classroom building.
3. Complete reroof of the entire campus- approximately 113,000 square feet including 13 buildings and several covered walkways.
4. Installation of a new tectum panel ceiling in the gymnasium.
5. Site Improvements to the front of the school to include a larger parking lot and new basketball court.
6. Demo and replacement of two existing chillers.

CURRENT STATUS (10/12/09):

Phase I New Cafetorium is complete, ahead of schedule.

Phase II is nearing completion, expected Substantial Completion to be the week of 10-19-09. Owner has targeted move in for November 09, nearly two months earlier than anticipated.

 

 

Charlotte High School Replacement

Nassau County: Callahan Middle Renovations

pinellas county Boca Ciega High School


pinellas County Leila Davis Elementary Classroom Additions


pinellas County Oakhurst Elementary Classroom Additions


pinellas County Ponce de Leon Elementary Classroom Additions


pinellas County Skyview Elementary Classroom Additions